How much earth comes out of the footings, how many trucks will cart it, how much goes back as backfill — and how much cut and fill will level the plot? The CivilOS Earthwork Calculator answers all four.
It uses the prismoidal formula for pits and trenches with sloping sides and the grid method for spot levels, and says so on the screen.
What you can do
| Feature | What it does | Export / status |
|---|---|---|
| Excavation | Pits and trenches: L, B, depth, working space, side slope, number | Free |
| Earth | In the ground, loose (swell), compacted (shrinkage); m³, cft, brass; truck loads | Free |
| Backfill | The space around what was built, compacted; surplus or shortfall | Free |
| Cut & fill | Grid of levels up to 12 × 12, formation level, balancing level | Free |
A worked example
Twelve 1.5 m square column footings 1.5 m deep with 300 mm working space and a 40 m plinth-beam trench 0.45 m wide and 0.6 m deep: 79.38 + 18.14 = 97.51 m³ in the ground, 121.9 m³ loose — 21 loads of a 6-wheel tipper. With 14 m³ of footings built in the pits, the backfill needs 92.8 m³ of earth as dug and about 5.9 m³ loose is left to cart away.
How to start
- Open CivilOS Tools and choose the Earthwork Calculator.
- Add the pits and trenches with their working space and slopes.
- Pick the soil and the truck.
- Type what is built in the pits for the backfill.
- Switch to Cut & fill for a plot's levels.
What CivilOS does not do
- No survey import. Levels are typed into the grid.
- No haul or machine costing. It gives the volumes and the loads.
Where a browser tool fits
Excavation is paid by the cubic metre in the ground and carted by the truck loose — two different numbers that are easy to confuse. Showing both, with the soil's swell and shrinkage named, avoids paying twice for the same earth.
Open the Earthwork Calculator free → no sign-inFrequently asked questions
How is the volume of a footing pit with sloping sides worked out?
The pit is a prismoid: its floor is the footing plus the working space each side, its top is wider by twice the slope times the depth, and V = D/6 × (A bottom + 4 × A middle + A top). A 1.5 m square footing 1.5 m deep with 300 mm working space and sides at ½ : 1 is 12.465 m³.
How is cut and fill worked out from levels?
On a grid of spot levels: each square whose four corners are all above the formation level is cut of its area × the mean depth (fill likewise); a square with corners on both sides is split by the four-point rule, cut = A/4 × (Σcut)² ÷ (Σcut + Σfill). The level that balances cut and fill is found by trial.
What are swell and shrinkage?
Earth dug out bulks up — the swell, about 25 % for ordinary soil — and is carted loose; rammed back it takes less room than it did in the ground — the shrinkage, about 10 %. The calculator offers typical figures for each soil; a soil report rules.
Is it free?
Yes, completely, with no account. It is part of CivilOS Tools. What you type is kept in your own browser, not on our server.
Draft for checking. Every safety-critical output of CivilOS is a preparation document. Drawings, quantities, rates, programmes and inspections must be verified, and the result signed off, by a licensed professional before they are issued, tendered, built or paid against.